Today is the last day of the 1st workshop. As a coincidence, the village organizes a village dancing night we plan to attend. But as planned, saturday morning was a regular working day.
Franišek Kurtin from
Ecoshop fixed the solar shower in the morning:
We attached the data logger to the cables - now we are able to measure the drying process as well:
David is finishing the reinforced plaster layer of the dome:
This is the view of the dome - we finished this part just as we planned:
Last bit of work inside - smoothening the surface of the dome. We can not introduce too much moisture:
The cleaning crew - straw can be used for everything:
The most important items - ventilators with 7000m3/h to dry the plaster. We have 4 of them in action for teh next week.
In the evening singing in the dome and saying goodby to the participants leaving:
LAter having fun at the village dancing evening:
The last participants are siting at the fire until early morning: